Sunday, November 26, 2006

Budget Reevaluation

So far, we have the following MUSTS in the budget before move-in:
* means work already has begun
PHASE 1
Popcorn Ceiling Removal + Paint $ 2000 saved $ 300 *
Paint Interior $ 900 saved@ $ 600 *
$ 300 wall prep
$ 100 Paint Sprayer
$500 Interior Paint
Termite Work $ 1992 saved $ 3000
Bullnose Corners $ 800 *

Carpet $ 1800
--------------------------------------------------------------
Phase 1 Total $7942

PHASE 2

Kitchen Cabinets $2500
Counter tops $1000
Kitchen Appliances $2000
Vinyl Windows $ 3558
___________________________________
Phase 2 Total $17000


PHASE 3 (est. costs)
Exterior Paint $1000 Save $500
Yard $3000
Pergo Floors $2000
Misc. (lighting, fixtures, etc) $1000

No comments: